Lanai at the Cove Walkway Replacement in Seaside, Oregon

  • Location: Seaside, Oregon
  • Client/Owner: Lanai at the Cove, a motel and condominium building on the Seaside oceanfront
  • Partners: The owners’ consulting engineer; City of Seaside
  • Year: 2011, design
  • Size/scale: About 80 feet of elevated walkway on a three-story wood-framed building, 40 feet on each of the second and third floors
  • JBE services: Site visit, structural design and calculations, construction drawings for bidding and permit, letter report
  • Sector: Multifamily & Housing
Three-story oceanfront condominium building in Seaside with open exit walkways on the second and third floors

The challenge

The Lanai at the Cove is a three-story wood-framed motel and condominium building facing the ocean in Seaside. Residents and guests reach the upper units along open walkways on the second and third floors of the east wing. The walkway decking was wood, and it sat exposed to coastal rain and weather. It had started to rot.

These walkways are the way out of the building, so the code holds them to a heavier load than an ordinary deck. A replacement had to last in salt air, carry exit loading, and get water off the walking surface instead of letting it soak in again.

Project photos

What we did

We visited the building in December 2010 and looked at the walkways and the framing below them. Then we designed a more durable replacement: 2-inch galvanized steel form deck with a lightweight concrete topping slab, spanning about 14 feet between the existing pressure-treated wood beams.

We checked the existing 6×10 beams for the weight of the new deck and concrete plus the 100 pounds per square foot live load the code requires for exiting. They were adequate, so the beams could stay and the work could be limited to the walking surface. To deal with the water, we detailed a shallow gutter along the outer edge of the slab, with drain lines through the half wall to downspouts.

We delivered calculations, a letter report and two sheets of construction drawings for the owners to use for contractor bids and the building permit.

The result

The owners received a permit-ready design in February 2011 that replaces rot-prone wood with steel and concrete, keeps the existing beams, and drains the walkways properly.

Related projects

Rebuilt covered walkway and new siding at a fire-damaged apartment building in Eugene, Oregon

Oakwood Manor Apartments Fire Rebuild

Eugene: A fire-damaged six-unit apartment building rebuilt to current code with new trusses, an accessible unit, sprinklers and restored stairs and walkways.

Habitat for Humanity structural engineering project, Eugene, Oregon — photo 4

Habitat for Humanity

Eugene, Springfield and Cottage Grove: pro-bono and discounted structural and civil work on about 30 Habitat for Humanity projects, 2004–2017.

Oakleigh Meadows co-housing structural engineering project, Eugene, Oregon — photo 2

Oakleigh Meadows Co-Housing

Eugene: structural design for a 28-home co-housing community of wood-framed buildings and a common house on a riverside site.

Three-story senior apartment building with balconies in Newport, Oregon

Big Creek Point Senior Apartments Fire Repair

Newport: Repair drawings to rebuild framing, a double-sided shearwall and the envelope after a sprinkler-stopped fire in a three-story senior apartment building.

Madison West Apartments in Eugene, Oregon, after conversion

Madison West Apartments Conversion, Eugene

Structural analysis and design to convert a former clinic in Eugene, Oregon, into apartments, with a new townhouse addition.